Loading articles...

Oilsands firms considering diluent recovery units to boost crude-by-rail volumes

Ongoing pipeline project delays and growth in crude-by-rail capacity from Western Canada are leading some oilsands producers to consider spending billions of dollars to build diluent recovery units. An oil worker holds raw sand bitumen near Fort McMurray, Alta., on July 9, 2008. THE CANADIAN PRESS/Jeff McIntosh

CALGARY — Ongoing pipeline project delays and growth in crude-by-rail capacity from Western Canada are leading some oilsands producers to consider spending billions of dollars to build diluent recovery units.

Oilsands bitumen is a thick, sticky oil which must be diluted with about half as much light petroleum to flow in a pipeline, but diluent isn’t needed for rail transport because the product can be heated for loading and unloading.

Eight Capital analyst Phil Skolnick says in a report that building diluent recovery units at Alberta rail-loading terminals would free up about one-third of the space in the railcar to improve the efficiency and overall profitability of sending bitumen by rail to refineries in the southern U.S.

In a recent interview, Cenovus Energy Inc. CEO Alex Pourbaix said his company is actively investigating building a unit at its terminal near Edmonton which would cost between $800 million and $1 billion.

He says it would be capable of processing up to 180,000 barrels per day of diluted bitumen, thus recovering about 60,000 barrels per day of diluent to be returned to its northern Alberta oilsands projects.

Rich Kruger, CEO of rival producer Imperial Oil Ltd., said on a recent conference call that his company has been considering building a diluent recovery unit for several years but has ruled against it for now because of the high cost and market uncertainties.

“DRUs in some cases can provide attractive returns, but more importantly, they can also improve the landscape of crude-by-rail and egress (to the tune of about 190,000 bpd of incremental bitumen if all 600,000 bpd of crude-by-rail used a DRU),” wrote Skolnick in his report.

“However, reduced costs and maximum diluent recycling are key to making this effort work. These current hurdles are likely reasons companies aren’t in a rush to build them yet.”

 

Companies in this article: (TSX:CVE, TSX:IMO)

The Canadian Press